
The original harbour station |
21
June
1836
Parliament
passed a
Private
Act (6
Wm.IV.,
cap.75)
incorporating
the
South
Eastern
and
Dover
Railway,
which
shortly
afterwards
changed
its name
to the
South
Eastern
Railway.
28
June
1843
the
South
Eastern
Railway
was
finished
as far
as a
temporary
station
at
Folkestone
and on
the 1st
July the
company
operated
a day
trip to
Boulogne
for
invited
guests.
1st
August
1843
the
first
scheduled
rail/sea
service
started
with
local
transport
being
offered
between
station
and
harbour.
October
1843
William
Cubitt
produced
a report
in
English
and
French
confirming
the
route of
the Nord
Railway
from
Amiens
to
Boulogne
along
the
route
that
was
subsequently
constructed.
18
December
1843
the
branch
railway
was
opened
for
traffic
as far
as a
coal
jetty.
It was
constructed
from the
first
permanent
station
to the
east of
the
Foord
Viaduct
and
logically
named ‘’Folkstone’’
(without
a middle
‘e’ and
later
Folkestone
Junction).
A plan
of 1843
shows a
new
railway
line
with
viaduct
arches,
possibly
a swing
bridge
and also
a new
hotel.
Harbour
House,
Packet
Office
and coal
store
are
shown
but
there is
no
indication
of a
station
on this
plan.
11
February
1844
Major
General
Pasley,
the
Railways
Inspector
presented
his
report
to the
Committee
of Privy
Council
after
visiting
on 30th
and 31st
January
1844 for
approval
of the
railway
for
freight
use to
the
termination
point of
Cubitt's
brick
viaduct.
Either
side of
the
viaduct
were
freight
jetties
constructed
of
wooden
piers
for use
by carts
and
wagons.
1847
the
first
swing
bridge
linked
the
viaduct
to the
spit of
recovered
land and
the
first
section
of
station
and
large
warehouse
were
finished
also
foundations
of a
southeast
facing
pier
were
laid.
The
railway
was and
is
unique
in that
it has
only one
station
at the
bottom
of a
1325
yard
double-track
branch
line,
laid at
a ruling
gradient
of 1 in
30.
Trains
did
operate
from the
platforms
at
Folkestone
Junction
to
Folkestone
Harbour
but this
depended
on them
heading
straight
into the
sidings
in order
to
reverse
direction
before
descending
the
‘hill’
to the
harbour.
The
harbour
jetty
was the
existing
double
track
viaduct
flanked
on
either
side by
wooden
piers
holding
a single
line.
1
January
1849,
following
The Nord
Railway's
completion
to
Boulogne
in 1848
and the
Board of
Trade
passing
the
Harbour
Branch
railway
for
passenger
train
use, the
world’s
first
international
fully
integrated
rail/sea/rail
service
commenced
between
London
and
Paris.
15
May 1855
the
Great
Gold
Robbery
took
place on
the
London -
Folkestone
boat
train
and was
only
discovered
when
weighed
in
Paris.
Various
staff at
Folkestone
Harbour
were
implicated.
One box
and its
lead
weight
contents
still
exist at
the
National
Railway
Museum.
1856
the
Railway
station
and
refreshment
rooms
were
re-constructed
and are
shown on
a plan
of that
year.
1893
the
original
swing
bridge
was
replaced
by a
second
structure
which
served
for 37
years
until
international
traffic
had
increased
to a
point
when the
harbour
station
had to
be
extended.
Rebuilding
of the
station
commenced
with the
two
platforms
rebuilt
around a
tight
curve to
give
access
to a
then
timber
pier.
The
first
four
sections
of
canopies
were
installed,
an
enclosed
lattice
footbridge
joined
the
platforms
and a
second
was
constructed
adjacent
to the
level
crossing.
The
goods
yard was
expanded
to a
complete
maze of
tracks
mirroring
the
station
platforms
with
their
tightly
curved
sidings.
Two
signal
boxes
were
built,
one at
each end
of the
station.
12
July
1904
The
French
Ambassador
opened
an
extended
station
complex
that
included
a
Customs
Hall,
Refreshment
Room,
Cloakrooms,
Lavatories
and
Ticket
Office.
1905
a single
wooden
platform
with
flat
canopy
was
erected
alongside
the ‘Up’
line,
south of
the
existing
station
and
physically
separated
from it
by
sidings
emerging
from the west.
Later
this
became
the
north
end of
the
first of
three
sections
of Pier
Platform
that
were
completed
on the
Outer
Pier and
covered
by a
unique
metal
canopy
constructed
to
protect
the
platforms
and
stabled
trains
from
shingle
washed
over the
harbour
wall
during
high
seas.
1914
- 1918
were war
years
and
these
are
described
in
"The
Military"
page.
Operationally
1915 saw
the
‘Down’
track
wagon
turntable
removed.
The
present
signal
box came
into use
upon the
northern
end of
the ‘Up’
platform,
built by
the now
South
Eastern
&
Chatham
Railway
to a
Saxby &
Farmer
design.
10
May 1930
the
Southern
Railway
removed
the
original
swing
bridge;
replacing
it over
a single
weekend
with the
present
one,
a now
unique
metal
Southern
Railway
replacement
was
rolled
into
place in
order to
allow
heavier
rolling
stock to
use the
station.
This
story is
graphically
told in
"The
Swingbridge"
page.
1938 saw
the
‘Down’
platform
extended
by 215
yards to
and new
canopies
installed,
virtually
doubling
its
length.
The ‘Up’
platform
could
not be
lengthened
because
of the
single
track
trailing
connection
with the
carriage
berthing
sidings.
This
meant
that the
‘Down’
platform
could
hold a
full
length
train
whereas
the ‘Up’
platform
was
split
and
could
only
hold
reduced
length
ones. At
the
southern
extremities
of both
the
‘Down’
and Pier
platforms
an
Exmouth
Junction
constructed
enclosed
concrete
footbridge
was
installed.
18
February
1960 new
colour
light
signalling
was
introduced
as part
of the
Kent
Coast
Electrification
scheme.
This was
controlled
by a
then new
power
box
installed
at
Folkestone
Junction
with the
SE&CR
cabin
remaining
in use
to
operate
the
level
crossing
and the
points
of the
platform
lines.
18
August
1968
was the
day that
freight
facilities
were
withdrawn
resulting
in the
lifting
of all
sidings
to the
east of
the
station
and use
of the
land for
car
ferry
purposes.
The
carriage
berthing
sidings
to the
west of
the
platforms
were
also
removed
and the
‘Up’
platform
extended
to join
with the
pier
platform.
1980
had
a
enclosed
transparent
footbridge
erected
over the
top of
the
original station
platforms,
replacing
the
earlier
open one.
This
provided
the ‘Up’
platform
with a
direct
link to
the
passenger
ferry
terminal
situated
immediately
adjacent
the
‘’down’’
side of
the
station.

Courtesy Roy Thornton collection. |
2001
saw
the
third
rail
de-energised
and the
''Up
Line''
taken
out of
use.
May
2002
somewhat
reversed
the
run-down
when the TPWS
safety
system
was
installed
along
the
remaining
line.
April
2006,
new
plans
were
published
showing
a total
redevelopment
of
Folkestone
Harbour.
This
included
the
conversion
of the
whole
harbour
site
into a
marina
with
permanent
closure
and
demolition
of the
railway
to make
way for
a dual
carriageway
road on
the
basis
that the
railway
split
Folkestone
in two
whereas
the road
would not.
12
April
2008, a
closure
ceremony,
together
with an
official
last
train
took
place
but
objections
by EWS,
the
Department
for
Transport
and
Southeastern
meant
that
this was
put off.
20
March
2009
Network
Rail
announced
that
they had
begun
the
formal
process
to close
the line
and this
threat
still
exists.
30
January
2011
The
Remembrance
Line
submitted
its
business
plan to
turn
back the
clock
and
re-start
boat
train
operation
in
connection
with
fast
ferries
to
Boulogne.